Liberals’ 2-year infrastructure plan set to take 5: documents

Government says 793 projects totalling $1.8 billion in federal funds have been granted extensions

Late last year, officials warned that a federal spending spree to repair crumbling roads and water systems could take three years longer than expected to complete, based on internal documents outlining issues with the first tranche of cash in the federal government’s infrastructure program.

The federal government had originally hoped to have cities and provinces complete $5.4 billion in transit and water system work by this March, but quickly realized that more time was needed.

A “secret” fall briefing note to Infrastructure Minister Amarjeet Sohi, obtained by The Canadian Press through the Access to Information Act, says delays hampered a large number of construction projects, requiring that the deadline be extended as far as March 2021.

The heavily blacked-out document predicted the majority of water and transit projects “would require extensions not only for a third year, but beyond into a fourth year (i.e. 2019-20) and fifth year (i.e. 2020-21),” referencing the federal fiscal years in brackets.

Sohi agreed to a blanket deadline extension to March 2020, turning what was to be a two-year stimulus program into a four-year plan.

He said the decision to grant extra time to 2020, instead of 2021, was based on the expected cash flow for projects and the ability for construction companies to handle all the extra work.

“This is not about that projects are being delayed, it’s about taking a little longer to complete those projects or taking a little longer to have the buses manufactured because of construction and manufacturing capacity,” Sohi said in an interview from Edmonton.

“From our perspective, we made a commitment to build and rebuild infrastructure and focus on the repairs in phase 1 and … we are achieving the results we intended to achieve, but we also want to give flexibility.”

As of Friday, the federal government had approved more than 3,400 water and transit projects with a combined federal contribution valued at almost $4.2 billion. Of that money, federal coffers had only doled out about $175.6 million to date, based on figures available on the Infrastructure Canada website.

Federal dollars flow once cities and provinces submit receipts for reimbursement, often creating a lag between when work takes place and when the federal money is spent.

In some cases, the federal government won’t receive receipts until a project is completely done. In other cases, projects are delayed because of labour strife, bad weather or other factors beyond Ottawa’s control.

The government says 793 projects representing about $1.8 billion in federal contributions have been granted individual extensions from Sohi. Between those extensions, and delays in filing expense claims, federal officials last year decided to shift more than $2 billion in planned spending to future years.

Provincial and municipal officials say that the time needed to go through the funding approval process contributed to the delays.

Having officials vet the details of each proposal before getting federal approval for funding meant some cities put off breaking ground until they knew federal funding would come their way.

“We heard loud and clear from some municipalities that they were struggling to meet two pieces of criteria: timeline requirements and a provision that would require municipalities to incur 60 per cent of their costs by March 31st, 2018,” said Alex Benac, a spokesman for Ontario Infrastructure Minister Bob Chiarelli.

The extra time and removal of the local spending requirement, which Chiarelli asked for in September, has given cities “much-needed time to get shovels in the ground and keep their projects on track according to a more generous, achievable timeline,” Benac said.

Federal and provincial officials say the lessons learned from the first phase of the program will be used in designing the second phase.

Both sides want funding agreements for the second, longer and more lucrative phase of infrastructure spending signed by March.

Jordan Press, The Canadian Press

Like us on Facebook and follow us on Twitter.

Just Posted

B.C. Green Party pushes for wild salmon commissioner

The role would serve as a unifying force in the provincial government

BC Ferries confirms Northern Sea Wolf will not sail until mid-July

BC Ferries had hoped to get the vessel in September of last year, but it didn’t arrive until December

UPDATED: Horgan says B.C. defending its interests in Trans Mountain pipeline

Canadian finance minister’s update comes the same day Kinder Morgan shareholders plan to meet

5 things to know about B.C. Floods 2018

Snowpacks continue to melt causing thousands to be displaced, dozens of local states of emergency

Police release video on how to ‘run, hide, fight’ if there’s an active shooter

Vancouver police offer video with input from E-Comm, BC EHS, Vancouver Fire and Rescue

B.C. dad pens letter urging overhaul of youth health laws after son’s fatal overdose

The Infants Act currently states children under 19 years old may consent to medical treatment on own

Singh sides with B.C. in hornet’s nest of pipeline politics for the NDP

Singh had called for a more thorough environmental review process on the proposal

VIDEO: Campers leave big mess at rural Vancouver Island campsite

Vehicle parts, garbage, a mattress, lawn chairs, beer cans, and even fecal matter left in the area

30 C in B.C., 30 cm of snow expected for eastern Canada

It might be hot in B.C., but the rest of Canada still dealing with cold

Horgan defends fight to both retain and restrict Alberta oil imports

Alberta says pipeline bottlenecks are kneecapping the industry, costing millions of dollars a day

RCMP caution boaters after two kids pass out from carbon monoxide poisoning

Both children were given oxygen and taken to hospital

Barkerville opens for the season

Highlights of Barkerville’s upcoming season include 150th Dominion Day and pack train re-creation

B.C. invests $115M to create 200 new nurse practitioner jobs

Health Minister says 780,000 B.C. residents don’t have a family doctor

Most Read