Site C dam project to miss river diversion deadline

Delay to add $610 million, estimate now near $9 billion

B.C. Hydro contractors have run into “geotechnical and construction challenges” that mean the Site C dam project will not be able to make its target of diverting the Peace River in the summer of 2019.

B.C. Hydro president Chris O’Riley confirmed the delay in a letter to the B.C. Utilities Commission, estimating an extra cost of $610 million that brings the total estimate to $8.9 billion for the most expensive construction project in B.C. history.

O’Riley said there is enough money in the project’s contingency fund for the cost, and a “one-year float” in the project schedule means it can still be completed as scheduled by November 2024. Other risks remain, including a road realignment to avoid evicting the last two holdout farming couples who live on the narrow riverside land and have already been paid in an expropriation to make way for the dam.

“Due to the project’s complexity, we expect to continue to face risks in other areas, including our second largest procurement (i.e. the generating station and spillway) that remains open and the highway realignment,” O’Riley wrote. “We will work to mitigate those challenges.”

The project is undergoing a review by the commission on the orders of Premier John Horgan, who made it a prominent issue during his years as NDP opposition leader. Under a tight deadline of Nov. 1 to make recommendations to the B.C. cabinet, the commission has already noted that Site C has been drawing heavily on contingency funds to deal with a tension crack in the riverbank and other issues.

Energy Minister Michelle Mungall said the delay is not a result of the NDP government’s review, ordered after former B.C. Hydro CEO Jessica Macdonald was fired this summer. The new government has commissioned reports on the cost of delaying or abandoning the project, which O’Riley says should continue after two years of work and nearly $2 billion spent.

“Despite the challenges we have encountered and the risks that remain, our analysis continues to confirm that completing Site C as planned is still the most cost-effective option for our customers,” O’Riley said. “Suspending or terminating and finding the power we need from other sources – which carries its own set of uncertainties – would cost billions more than completing Site C.”

BC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

New MP Taylor Bachrach makes his first trip to Bella Coola

Bachrach said he is keen to get to know his riding and the members of his constituency

Bachrach rejects calls for police action against demonstrators

Skeena-Bulkley Valley MP says only way out of crisis is “true nation-to-nation” talks

Nuxalk Nation celebrates first carpentry graduates

11 students graduated from the community’s first carpentry program

Bella Coola leave their mark on All Native Basketball Tournament as they reach Intermediate final

Nuxalk Braves bring home a strong second place finish; three individual awards for Marlon Edgar-Apps

All Native Basketball: Finals matchups start to take shape as title games approach

Two Prince Rupert sides in contention, while two dynasties are on the brink

Blair says RCMP have met Wet’suwet’en conditions, calls for end to blockades

The Wet’suwet’en’s hereditary chiefs oppose the Coastal GasLink project

Petition seeks to remove local police department from Lindsay Buziak murder case

American woman starts online petition in hopes of helping Buziak family

Health officials confirm sixth COVID-19 case in B.C.

Woman remains in isolation as Fraser Health officials investigate

Study says flu vaccine protected most people during unusual influenza season

Test-negative method was pioneered by the BC Centre for Disease Control in 2004

Saskatchewan and B.C. reach championship round at Scotties

British Columbia’s Corryn Brown locked up the last berth in Pool B

B.C. lawyer, professor look to piloting a mental-health court

In November, Nova Scotia’s mental-health court program marked 10 years of existence

COLUMN: Not an expert on First Nations government structures? Then maybe you should calm down

Consider your knowledge about First Nations governance structures before getting really, really mad

Meet the Wet’suwet’en who want the Coastal GasLink pipeline

Supporters of the pipeline are upset only one side is being heard nationwide

One dead in multi-vehicle collision involving logging truck on northern B.C. highway

DriveBC says highway expected to remain closed until 8 p.m.

Most Read