Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

Just Posted

“Does Kirby care?” Heiltsuk Nation using geo-targeted ads in Houston, Texas for justice

The Heiltsuk Tribal Council has called out Kirby Corporation for the Nathan E. Stewart oil spill

“No excuse” for killing of two young grizzly cubs

Reader hopeful someone will come forward with information

UPDATE: U.S. firm fined $2.9M for fuel spill that soiled B.C. First Nation territory

The Nathan E. Stewart spilled 110,000 litres of diesel and heavy oils in October 2016

No delivery services hard on local families

New parents Candace Knudsen and Bjorn Samuelsen spent five weeks away from home

Rich the Vegan scoots across Canada for the animals

Rich Adams is riding his push scooter across Canada to bring awareness to the dog meat trade in Asia

Canadian high school science courses behind on climate change, says UBC study

Researchers found performance on key areas varies by province and territory

Six inducted into BC Hockey Hall of Fame

The 26th ceremony in Penticton welcomed powerful figures both from on and off the ice

RCMP investigate two shootings in the Lower Mainland

Incidents happened in Surrey, with a victim being treated at Langley Memorial Hospital

CRA program to help poor file taxes yields noticeable bump in people helped

Extra money allows volunteer-driven clinics to operate year-round

Recall: Certain Pacific oysters may pose threat of paralytic shellfish poisoning

Consumers urged to either return affected packages or throw them out

How a Kamloops-born man helped put us on the moon

Jim Chamberlin did troubleshooting for the Apollo program, which led to its success

Sexual harassment complaints soaring amid ‘frat boy culture’ in Canada’s airline industry

‘It’s a #MeToo dumpster fire…and it’s exhausting for survivors’

How much do you know about the moon?

To mark the 50th anniversary of the first lunar landing, see how well you know space

Most Read