Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Danika Naccarella to receive BC Creative Achievement Award

For the past few years Danika Naccarella’s career has been enjoying a steady upward trajectory

New multi-use trail taking shape in Hagensborg

Recreation Sites and Trails BC (RSTBC) is funding a new section of trail in Hagensborg

BC Ferries restricts passengers from lower vehicle decks

The new regulations will no longer allow passengers to remain in their vehicles on closed car decks.

VIDEO: Sears liquidation sales continue across B.C.

Sales are expected to continue into the New Year

B.C. NDP convention set for Victoria

Premier, federal leader Jagmeet Singh to add energy

Silver Creek farm search expands north

RCMP were seen collecting evidence three kilometres north of the farm where human remains were found

B.C. school trustee calls LGBTQ school program ‘weapon of propaganda’

Chilliwack’s Barry Neufeld published the comments on his Facebook page

B.C. couple hope boat drone becomes first to cross Atlantic

Colin and Julie Angus of Victoria to have drone collect environmental data en route

B.C. casino accused of illegal activity follows rules: operator

B.C. had launched review after concerns about money laundering at River Rock casino in Richmond

Opponents of LGBTQ program to file human rights complaint against Surrey School District

District denied Parents United Canada right to rent Bell Performing Arts Centre for rally next month

Ex-employee describes alleged sexual assault by B.C. city councillor

Complainant was a teen during the alleged 1992 incident

Amazon gets 238 proposals for 2nd headquarters

Submissions were due last week. Online retailer has said tax breaks and grants would be factors

Most Read